S E R V I C I N G A N D I N S P E C TI O N
140
First inspection after 50 operating hours
Tasks to be performed (check) 50 hours inspection
Check the transmission, engine and hydraulic system for leaks
Check the hydraulic, engine coolant and engine oil coolers for dirt
Check the coolant level and antifreeze
Check the tension and condition of the V-belt
Make sure all hoses and pipes t tightly
Check the routing of the hoses and pipes
Check the piston rods for the hydraulic cylinders for damage or dirt
Check the routing of the bowden cables and electrical wiring
Retighten all the fasteners. Observe in particular the engine suspension, axle mounting and drive shaft
Check: Instruments + audible warning devices
Maintenance and inspection personnel must have
specialized knowledge of servicing and inspection
work on the loader.
Follow the Operator’s Manual for the engine.
To assure proper functioning of the machine, it is
required that the rst inspection be performed af-
ter 50 operating hours, but at the latest 3 months
after initial start-up, by a Wacker Neuson dealer
or a mechanic at a Wacker Neuson factory agent.